West Return Floodwall, Northern Segment.

Contractor Name: Odebrecht-Johnson Bros Joint Venture
Description of work: The work under this contract consists of excavation of a floatation channel, clearing and grubbing, installation of steel sheet piling, prestressed concrete piling, steel H-piling, reinforced concrete floodwalls, stone placement, painting, swing gate, demolition of existing floodwall, modification of existing pump station discharge pipes, asphaltic pavement, turf establishment and maintenance.
Award Amount: $82,642,364.60
Award Date: July 15, 2010
Notice to Proceed Acknowledged: August 6, 2010
Required Completion Date: Phase 1 – December 9, 2011 (490 calendar days)
Phase 2 – April 6, 2012 (609 calendar days)

Any issues, problems or complaints should be referred to: U.S. Army Corps of Engineers Construction Impact Hotline at 1-877-427-0345